DZRH Logo
EDSA barriers restored after MMDA flags unauthorized movement by contractor
EDSA barriers restored after MMDA flags unauthorized movement by contractor
Metro Manila
EDSA barriers restored after MMDA flags unauthorized movement by contractor
by Thea Divina26 November 2026
FILE PHOTO VIA RH EDNIEL PARROSA

Concrete barriers along EDSA near Annapolis were being returned to their original positions Thursday morning after the Metropolitan Manila Development Authority (MMDA) flagged their unauthorized relocation by a private contractor.

The MMDA fined Readycon Trading and Construction Corp. ₱50,000 for allegedly moving the barriers along the EDSA Busway without authorization on Nov. 20.

According to a report by RH Edniel Parrosa, as of 8:25 a.m. Thursday, Nov. 26, workers were still repositioning the barriers, causing heavy traffic in the area as the work coincided with the morning rush hour.

The restoration also exposed uneven asphalt on the road, a result of the ongoing second phase of the EDSA rehabilitation project.

Readycon reportedly moved the barriers to cover unfinished asphalt overlay work along the innermost lane, which is designated for buses.